NextEra Energy revamping Cerro Gordo Wind Farm

The company held an open house in Mason City, inviting residents to learn about the project.

Posted: Sep 10, 2019 10:17 PM
Updated: Sep 11, 2019 7:42 AM

MASON CITY, Iowa - It's been nearly 20 years since the Cerro Gordo Wind Farm first started cranking out electricity. 

Now the owner of the turbines says it's time for an upgrade.

NextEra Energy plans to replace the 55 turbines currently in the wind farm with 15 new ones.  The project manager says technology has improved a lot over the years, and that the 15 new turbines will generate as much power as the 55 old turbines.  

The project will cost about $50 million.  Construction will begin in February of 2020 and should wrap up in July of that year.

Article Comments

Mason City
Clear
60° wxIcon
Hi: 83° Lo: 59°
Feels Like: 60°
Albert Lea
Clear
63° wxIcon
Hi: 80° Lo: 61°
Feels Like: 63°
Austin
Clear
66° wxIcon
Hi: 83° Lo: 63°
Feels Like: 66°
Charles City
Clear
64° wxIcon
Hi: 78° Lo: 60°
Feels Like: 64°
Rochester
Clear
62° wxIcon
Hi: 81° Lo: 60°
Feels Like: 62°
A final blast of summer weather before meteorological fall in one week.
KIMT Radar
KIMT Eye in the sky

Latest Video

Image

Weather Forecast 9/15

Image

Learning about water quality

Image

Tracking the Monarch butterfly's flight path

Image

Filling the boot for Easter Seals

Image

WEATHER FORECAST 2 9/14

Image

'We won't stay silent' walk raises awareness for recovery

Image

Providing smoke alarms to homes in Southeast Minnesota.

Image

Walking to end Alzheimer's

Image

Sports OT: Part 2

Image

Sports Overtime Part 1

Community Events